These activities will be the template for the Production cutover plan - so please update with any activities that are required for the Sandbox and Production migrations.

Steps for Interim period:

  • HCM Role Assignments complete by 6/29. Kelli to validate
  • 7/6 - Kelli will 'Maintain Roles' in HCM RBA to remove Department and Department Hierarchy.
  • Integration will not be ready on 7/25 - manual beginning 7/25
  • Refresh UVA3 - 
    • UVA7 scheduled for 7/4 - Bo could do some development for ResearchUVA.
    • 8/13 - Refresh UVA3


IDTaskAssigned ToFST StatusHCM StatusStart DateDue DateNotes

Identify Proxy ListTeresa

Complete

Complete

Send list of testers that should be able to Proxy in SBX (for Regression test) to Kelli.


Provide access to Production/SBXKelli/Venkat

Complete

CompleteMonday, June 27Friday, July 1Matt and Litao confirmed prod access on 6/15

Create Data Steward/MBU Approver Security Groups in ProdMatt

Complete

CompleteTuesday, July 5Friday, July 8



Create Role Assignee EIBMatt

Complete

n/a

contingent on data steward security groups in prod

Promote Extend Application to Production/SBXLitao

Complete

CompleteThursday, June 30



Copy Test scenarios to Regression Test Scenarios in TAPPLeslieCompleteCompleteJuly 6July 8Teresa to add scenarios - and then ready for copy.

Update Security Group Reference ids in Production.Matt

complete

completeTuesday, July 5Friday, July 8

Confirm for SBX/Prod


Add Data Steward groups to Personal Data Other IDs domain, view only - PRODMatt

Complete

In ProgressTuesday, July 5Friday, July 8

Needed to see Computing ID.

Complete in SBX - needs to be done in Prod.

Matt's 7/23 update - confirmed all data steward (and MBU approver) security groups have view access on Person Data: Other IDs


Update segmented security Matt

TBD

TBDTuesday, July 5Friday, July 8

A new segmented group to give users the ability to view the bp details.

Matt to confirm whether this is needed.

7/7 - this may not be needed; BP segment domain to run reports; potentional use case for HR and Finance admins



Apply permissions and Users to Disposition Lists - in Production/SBX MattIn ProgressIn ProgressTuesday, July 5Friday, July 8

Dependent on Security Group activities above.

Disposition Dashboard


Add assignees to Data Steward/MBU Approver Security Groups in Production/SBX (via EIB)Matt

Complete

CompleteTuesday, July 5Friday, July 8

Dependent on Creation of Security groups and the Reference IDs. Kelli to add to prod before SBX refresh.


Custom TasksLitao

Complete

CompleteTuesday, July 5Friday, July 8

Do only in SBX and only do in Production when going live


Setup External Client Cred StoreLitao

Complete

CompleteTuesday, July 5Friday, July 8Litao can help

Change Role names in Production

Kelli

In Progress

In ProgressTuesday, July 5Friday, July 8

Matt can help - please confirm UVA3 is correct by 7/20 in order for Matt to complete by 7/22.

Unable to locate Jira server for this macro. It may be due to Application Link configuration.

Unable to locate Jira server for this macro. It may be due to Application Link configuration.


Calculated fields

Litao (Extend pages)  & Matt (BP)

Complete

Complete

Tuesday, July 5Friday, July 8

After groups are created.  Will use OX and should take approx an hour.


Condition rules (BP step conditions)

Matt

Complete

CompleteTuesday, July 5Friday, July 8

After groups are created


SBX Refresh from ProdWorkdayComplete
Friday, July 8


Smoke Test Config in SBXMatt

Complete

CompleteJuly 11July 22



Smoke Test Extend in SBXLitao

Complete

CompleteJuly 11July 22

Make the Custom Dashboards avail in SBXLitao

Complete

CompleteJuly 11


Verify/Update Proxy and Security for HCM/FST TeamsKelli

Complete

CompleteJuly 11


Unhide the details to the Announcements page in SBXKelli

N/A

N/AJuly 11
Need the FIN Website

Confirm Smoke Test complete - Ready for UVA ValidationLitao & Matt

Complete

CompleteJuly 12
Litao and Matt to notify: Kelli, Teresa, Crystal, Sue, Nicole 

Regression Test in SBX

FST & HCM Team

In Progress

In ProgressJuly 12

July 22

FST: Crystal, Mandy, Rylee, Steve Fielding, Josh

HCM: Kelli, Teresa


Need MBU security group members confirmationTeresa/Nicole/MattCompleten/aFriday, July 1Friday, July 15

Matt to provide current assignees (can be updated in prod later)

Teresa to ask Nicole for confirmation

Want this in time for Regression Testing - 7/15 is latest


SBX Refresh from ProdWorkdayComplete
Friday, July 15


Ensure the training approvers are:

    1. Danielle Hancock
    2. Erika Priddy
    3. Jack Jensen
    4. Linda Leshowitz
    5. Nasima Andesha
    6. Patty Marbury
MattNot Startedn/aFriday, July 22
Matt's 7/23 update – confirmed these users are assigned to Finance Training user-based group used in approval step

Ensure all the MBU approvers are the ones provided in Nicole’s list in  w Unable to locate Jira server for this macro. It may be due to Application Link configuration.

MattNot Startedn/aFriday, July 22


HCM & FST: Send Test transaction in Prod

Team


Not Started

Not StartedThursday July 21

During team call

Use a direct link (bypass dashboards)


Configure Custom Task and Dashboard in Production

Custom Dashboards (Admin Requests and My Requests) 

Kelli

Not Started

Not StartedSunday, July 24

Kelli and Matt to write down the steps:

  • Add the Worklet as Required.
  • Update condition rule on tab on Content page of Custom Page for System Access Requests (so it becomes visible)

System Access Request the Default Tab Needs to be removed (UVA-397)KelliNot StartedNot StartedMonday July 25

The System Access Request TAB shows in UVA3 and it should be removed or included in the go-live steps to be removed.

Unable to locate Jira server for this macro. It may be due to Application Link configuration.


Allow Delegation for HCM and FST

Unable to locate Jira server for this macro. It may be due to Application Link configuration.

Unable to locate Jira server for this macro. It may be due to Application Link configuration.

KelliNot StartedNot StartedMonday July 25


Validate Website links are valid (if applicable)Kelli

Not Started

Not StartedMonday July 25
FST page link on the IT RBA page and in the Announcements.

Activate Announcements with instructions on Updating your Desktop.Kelli

Not Started

N/AMonday, July 25



Send Test transaction (during 9am checkin)

HCM: Kelli

FST: Sue

Not Started

Not StartedMonday, July 25

Identify any approvers



Project Team Check-in Teresa/Leslie

Not Started

Not StartedMonday, July 25
Schedule check-in at 9am ET. (team call)

Announce App is liveTeresa

Not Started

Not StartedMonday, July 25



Post Announcement on ITS Website 

Teresa

Not Started

Not StartedMonday, July 25Monday, July 25Announcement includes the Data Stewards

Send email to Stakeholders on go-live day

FST: James, Sue

HCM: Susanna

Not Started

Not StartedMonday, July 25

FST: James/Communication & Change Team

Angela Knobloch, FST change team

Brandi Van Ormer, FST comms

HCM: Susanna Fuller


Migrate Integration to  ProductionSri & Litao

Not Started

Not StartedTBDTBDDependent on INT - timing TBD

Confirm Report Ownership to ISU (Integration)Sri & Litao

Not Started

Not StartedTBDTBDDependent on INT - timing TBD