These activities will be the template for the Production cutover plan - so please update with any activities that are required for the Sandbox and Production migrations.
Steps for Interim period:
- HCM Role Assignments complete by 6/29. Kelli to validate
- 7/6 - Kelli will 'Maintain Roles' in HCM RBA to remove Department and Department Hierarchy.
- Integration will not be ready on 7/25 - manual beginning 7/25
- Refresh UVA3 -
- UVA7 scheduled for 7/4 - Bo could do some development for ResearchUVA.
- 8/13 - Refresh UVA3
ID | Task | Assigned To | FST Status | HCM Status | Start Date | Due Date | Notes |
---|---|---|---|---|---|---|---|
Identify Proxy List | Teresa | Complete | Complete | Send list of testers that should be able to Proxy in SBX (for Regression test) to Kelli. | |||
Provide access to Production/SBX | Kelli/Venkat | Complete | Complete | Monday, June 27 | Friday, July 1 | Matt and Litao confirmed prod access on 6/15 | |
Create Data Steward/MBU Approver Security Groups in Prod | Matt | Complete | Complete | Tuesday, July 5 | Friday, July 8 | ||
Create Role Assignee EIB | Matt | Complete | n/a | contingent on data steward security groups in prod | |||
Promote Extend Application to Production/SBX | Litao | Complete | Complete | Thursday, June 30 | |||
Copy Test scenarios to Regression Test Scenarios in TAPP | Leslie | Complete | Complete | July 6 | July 8 | Teresa to add scenarios - and then ready for copy. | |
Update Security Group Reference ids in Production. | Matt | complete | complete | Tuesday, July 5 | Friday, July 8 | Confirm for SBX/Prod | |
Add Data Steward groups to Personal Data Other IDs domain, view only - PROD | Matt | Complete | In Progress | Tuesday, July 5 | Friday, July 8 | Needed to see Computing ID. Complete in SBX - needs to be done in Prod. Matt's 7/23 update - confirmed all data steward (and MBU approver) security groups have view access on Person Data: Other IDs | |
Update segmented security | Matt | TBD | TBD | Tuesday, July 5 | Friday, July 8 | A new segmented group to give users the ability to view the bp details. Matt to confirm whether this is needed. 7/7 - this may not be needed; BP segment domain to run reports; potentional use case for HR and Finance admins | |
Apply permissions and Users to Disposition Lists - in Production/SBX | Matt | In Progress | In Progress | Tuesday, July 5 | Friday, July 8 | Dependent on Security Group activities above. Disposition Dashboard | |
Add assignees to Data Steward/MBU Approver Security Groups in Production/SBX (via EIB) | Matt | Complete | Complete | Tuesday, July 5 | Friday, July 8 | Dependent on Creation of Security groups and the Reference IDs. Kelli to add to prod before SBX refresh. | |
Custom Tasks | Litao | Complete | Complete | Tuesday, July 5 | Friday, July 8 | Do only in SBX and only do in Production when going live | |
Setup External Client Cred Store | Litao | Complete | Complete | Tuesday, July 5 | Friday, July 8 | Litao can help | |
Change Role names in Production | Kelli | In Progress | In Progress | Tuesday, July 5 | Friday, July 8 | Matt can help - please confirm UVA3 is correct by 7/20 in order for Matt to complete by 7/22.
| |
Calculated fields | Litao (Extend pages) & Matt (BP) | Complete | Complete | Tuesday, July 5 | Friday, July 8 | After groups are created. Will use OX and should take approx an hour. | |
Condition rules (BP step conditions) | Matt | Complete | Complete | Tuesday, July 5 | Friday, July 8 | After groups are created | |
SBX Refresh from Prod | Workday | Complete | Friday, July 8 | ||||
Smoke Test Config in SBX | Matt | Complete | Complete | July 11 | July 22 | ||
Smoke Test Extend in SBX | Litao | Complete | Complete | July 11 | July 22 | ||
Make the Custom Dashboards avail in SBX | Litao | Complete | Complete | July 11 | |||
Verify/Update Proxy and Security for HCM/FST Teams | Kelli | Complete | Complete | July 11 | |||
Unhide the details to the Announcements page in SBX | Kelli | N/A | N/A | July 11 | Need the FIN Website | ||
Confirm Smoke Test complete - Ready for UVA Validation | Litao & Matt | Complete | Complete | July 12 | Litao and Matt to notify: Kelli, Teresa, Crystal, Sue, Nicole | ||
Regression Test in SBX | FST & HCM Team | In Progress | In Progress | July 12 | July 22 | FST: Crystal, Mandy, Rylee, Steve Fielding, Josh HCM: Kelli, Teresa | |
Need MBU security group members confirmation | Teresa/Nicole/Matt | Complete | n/a | Friday, July 1 | Friday, July 15 | Matt to provide current assignees (can be updated in prod later) Teresa to ask Nicole for confirmation Want this in time for Regression Testing - 7/15 is latest | |
SBX Refresh from Prod | Workday | Complete | Friday, July 15 | ||||
Ensure the training approvers are:
| Matt | Not Started | n/a | Friday, July 22 | Matt's 7/23 update – confirmed these users are assigned to Finance Training user-based group used in approval step | ||
Ensure all the MBU approvers are the ones provided in Nicole’s list in w | Matt | Not Started | n/a | Friday, July 22 | |||
HCM & FST: Send Test transaction in Prod | Team | Not Started | Not Started | Thursday July 21 | During team call Use a direct link (bypass dashboards) | ||
Configure Custom Task and Dashboard in Production Custom Dashboards (Admin Requests and My Requests) | Kelli | Not Started | Not Started | Sunday, July 24 | Kelli and Matt to write down the steps:
| ||
System Access Request the Default Tab Needs to be removed (UVA-397) | Kelli | Not Started | Not Started | Monday July 25 | The System Access Request TAB shows in UVA3 and it should be removed or included in the go-live steps to be removed.
| ||
Allow Delegation for HCM and FST
| Kelli | Not Started | Not Started | Monday July 25 | |||
Validate Website links are valid (if applicable) | Kelli | Not Started | Not Started | Monday July 25 | FST page link on the IT RBA page and in the Announcements. | ||
Activate Announcements with instructions on Updating your Desktop. | Kelli | Not Started | N/A | Monday, July 25 | |||
Send Test transaction (during 9am checkin) | HCM: Kelli FST: Sue | Not Started | Not Started | Monday, July 25 | Identify any approvers | ||
Project Team Check-in | Teresa/Leslie | Not Started | Not Started | Monday, July 25 | Schedule check-in at 9am ET. (team call) | ||
Announce App is live | Teresa | Not Started | Not Started | Monday, July 25 | |||
Post Announcement on ITS Website | Teresa | Not Started | Not Started | Monday, July 25 | Monday, July 25 | Announcement includes the Data Stewards | |
Send email to Stakeholders on go-live day | FST: James, Sue HCM: Susanna | Not Started | Not Started | Monday, July 25 | FST: James/Communication & Change Team Angela Knobloch, FST change team Brandi Van Ormer, FST comms HCM: Susanna Fuller | ||
Migrate Integration to Production | Sri & Litao | Not Started | Not Started | TBD | TBD | Dependent on INT - timing TBD | |
Confirm Report Ownership to ISU (Integration) | Sri & Litao | Not Started | Not Started | TBD | TBD | Dependent on INT - timing TBD | |