These activities will be the template for the Production cutover plan - so please update with any activities that are required for the Sandbox and Production migrations.


IDTaskAssigned ToFST StatusHCM StatusStart DateDue DateNotes

Identify Proxy ListTeresa

Not Started

Not Started

Send list of testers that should be able to Proxy in SBX (for Regression test) to Kelli.


Provide access to Production/SBXKelli/Venkat

Complete

CompleteMonday, June 27Friday, July 1Matt and Litao confirmed prod access on 6/15

Create Data Steward/MBU Approver Security Groups in ProdKelli/Matt

Not Started

Not StartedTuesday, July 5Friday, July 8

Could begin earlier if testing signoff is before 7/5


Create Role Assignee EIBMatt

Complete

n/a

contingent on data steward security groups in prod

Promote Extend Application to Production/SBXLitao

Not Started

Not StartedThursday, June 30



Update Security Group Reference ids in Production.Kelli/Matt

Not Started

Not StartedTuesday, July 5Friday, July 8

Confirm for SBX/Prod


Add Data Steward groups to Personal Data Other IDs domain, view only - PRODMatt/Kelli

Not Started

Not StartedTuesday, July 5Friday, July 8Needed to see Computing ID.

Kelli to update segmented security.  Kelli

Not Started

Not StartedTuesday, July 5Friday, July 8

A new segmented group to give users the ability to view the bp details.


Apply permissions and Users to Disposition Lists - in Production/SBX Kelli/Matt

Not Started

Not StartedTuesday, July 5Friday, July 8

Dependent on Security Group activities above.

Disposition Dashboard


Add assignees to Data Steward/MBU Approver Security Groups in Production/SBX (via EIB)Matt

Not Started

Not StartedTuesday, July 5Friday, July 8

Dependent on Creation of Security groups and the Reference IDs. Kelli to add to prod before SBX refresh.


Custom TasksLitao

Not Started

Not StartedTuesday, July 5Friday, July 8

Do only in SBX and only do in Production when going live


Setup External Client Cred StoreKelli

Not Started

Not StartedTuesday, July 5Friday, July 8

Custom Dashboards (Admin Requests and My Requests) in SBXKelli/Matt

Not Started

Not StartedTuesday, July 5Friday, July 8

Dependent on Custom Tasks.

Create the tab for users, create worklet for users.

Kelli will set in Prod and hide. 


Migrate Integration to  ProductionSri & Litao

Not Started

Not StartedTBDTBDDependent on INT - timing TBD

Confirm Report Ownership to ISU (Integration)Sri & Litao

Not Started

Not StartedTBDTBDDependent on INT - timing TBD
XXChange Role names in Production

Kelli

Not Started

Not StartedTuesday, July 5Friday, July 8



Calculated fields

Litao (Extend pages)  & Matt (BP)

Not Started

Not StartedTuesday, July 5Friday, July 8

After groups are created.  Will use OX and should take approx an hour.


Condition rules (BP step conditions)

Matt

Not Started

Not StartedTuesday, July 5Friday, July 8

After groups are created


SBX Refresh from ProdWorkdayNot Started
Friday, July 8


Smoke Test Config in SBXMatt

Not Started

Not StartedJuly 11July 22



Smoke Test Extend in SBXLitao

Not Started

Not StartedJuly 11July 22

Make the Custom Dashboards avail in SBXKelli

Not Started

Not StartedJuly 11


Verify/Update Proxy and Security for HCM/FST TeamsKelli

Not Started

Not StartedJuly 11


Unhide the details to the Announcements page in SBXKelli

Not Started

Not StartedJuly 11


Confirm Smoke Test complete - Ready for UVA ValidationLitao & Matt

Not Started

Not StartedJuly 12
Litao and Matt to notify: Kelli, Teresa, Crystal, Sue, Nicole 

Regression Test in SBX

FST & HCM Team

Not Started

Not StartedJuly 12

July 22

FST: Crystal, Sue, Nicole

HCM: Kelli, Teresa


SBX Refresh from ProdWorkdayNot Started
Friday, July 15


SBX Steps - insert






HCM & FST: Send Test transaction in Prod

Team


Not Started

Not StartedThursday July 21
During team call

Configure Custom Task and Dashboard in ProductionKelli/Matt

Not Started

Not StartedSunday, July 24

Kelli and Matt to write down the steps:

  • Add the Worklet as Required.
  • Update condition rule on tab on Content page of Custom Page for System Access Requests (so it becomes visible)

Validate Website links are valid (if applicable)Kelli

Not Started

Not StartedMonday July 25


Activate Announcements with instructions on Updating your Desktop.Kelli

Not Started

Not StartedMonday, July 25



Send Test transaction (during 9am checkin)

HCM: Kelli

FST: Sue

Not Started

Not StartedMonday, July 25

Identify any approvers



Project Team Check-in Teresa/Leslie

Not Started

Not StartedMonday, July 25
Schedule check-in at 9am ET. (team call)

Announce App is liveTeresa

Not Started

Not StartedMonday, July 25

Wait until the Disposition call at noon ET.


Post Announcement on ITS Website 

Teresa

Not Started

Not StartedMonday, July 25Monday, July 25Announcement includes the Data Stewards

e-Sharp closes for new FST requestsTeresa

Not Started

n/aMonday, July 25

New requests will not be allowed after 5pm.

In Progress requests will complete in e-Sharp.

Note: In flight requests will remain in e-Sharp until they are completed.


Send email to Stakeholders on go-live day

FST: Sue

HCM: Amanda

Not Started

Not StartedMonday, July 25