Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Based on the FNAL "Approved" procedure on https://seaquest-docdb.fnal.gov/cgi-bin/sso/ShowDocument?docid=10355
Demonstration Video (Note: Please ignore the Steps with the "Iron Cage" as it was replaced with a storage cabinet in the very recent approved version):
https://drive.google.com/file/d/18QMZcQo55Yr2iqhSTFtNA3yn9LO8JOMZ/view?usp=sharing

Loading the Insert (All target members at Counting House should help organize when this is an ammonia loading job)

StepTime frameLocationPersonnelCritical Points
1Day BeforeNM4 Target Loading Area

Target Insert Team

NMR Team

Depending Infrastructure Checks: Make sure insert coils and temperatures sensors are working.  Check that each NMR coil is able to see the crystal signal.  Check the each Cernox is work in LN2.  Make sure each Q-meter is working and each Lambda/2 cable is connected well and you have seen a crystal signal with each prior to target insert installation.  Make sure microwave have been tested and all is ready.
2
NM4 Target Loading AreaAny Target Team memberStage the Target Loading: Fill the target loading tub with LN2 at least 30 minutes ahead.  It will take 5 trips.  This should be done before calling the RSO, IH, ES&H or anyone else that is coming out to watch.  At this time check that the tools that are needed are laid out on the table, that the microwave and NMR tools are in the little plastic bag on the insert rack, that the insert handle is on the insert, that the screw driver for the lids is there.
2
Target Controls (Counting House)Target ExpertClose Gate valve and GV-bypass.  





Checklist for Unloading the insert without NH3/ND3

...