Loading the Insert (All target members at Counting House should help organize when this is an ammonia loading job)

StepTime frameLocationPersonnelCritical Points
1Day Before

NM4 Target Loading Area

Cryo-platform 

Target Insert Team

NMR Team

Infrastructure Checks: Make sure insert coils and temperatures sensors are working.  Check that each NMR coil is able to see the crystal signal.  Check the each Cernox is work in LN2.  Make sure each Q-meter is working and each Lambda/2 cable is connected well and you have seen a crystal signal with each prior to target insert installation.  Make sure microwave have been tested and all is ready.
21 hour beforeNM4 Target Loading AreaAny Target Team memberStage the Target Loading: Fill the target loading tub with LN2 at least 60-30 minutes ahead.  It will take 5 trips.  This should be done before calling the RSO, IH, ES&H or anyone else that is coming out to watch.  At this time check that the tools that are needed are laid out on the table, that the microwave and NMR tools are in the little plastic bag on the insert rack, that the insert handle is on the insert, that the screw driver for the lids is there.
3Before going into HallTarget Controls (Counting House)Target ExpertClose gate valve and GV-bypass for backfilling, ensure the fridge is no fuller than 20% otherwise boil it off with the annealing plates, ensure the target actuator position is in Middle position.
4Before going inHall Corridor into NM4Target Loading TeamEnsure PPE for the occasion is used and that you sign the RWP (they check).  Obtain material from shed and bring it down to NM4 and put in LN2 bath ready for loading.
5During ProcedureNM4 Target Loading AreaTarget Loading TeamLoad target.  Take photo of the bottle before loading and bottle label.  After loading take photo of the loaded insert before putting lid on.
6During ProcedureNM3 CaveTarget Loading TeamCheck that there is a backup seal available. Load insert.  Connect NMR cables and microwaves.  Put tools back in little plastic bag.  Turn off cave light.
7After procedureTarget Controls (Counting House)Target ExpertOpen gv-bypass or gate valve. As soon as possible after the target insert is loaded the Target Expert should fill the fridge to keep material cold.
8After procedureTarget Controls (Counting House)Target ExpertAfter procedure update the target inventory and post an FNAL elog about what material is in each target location.

Unloading the Insert (All target members at Counting House should help organize when this is an ammonia unloading job)

StepTime frameLocationPersonnelCritical Points
11 or  days before
Target ExpertNotify RSO, ES&H
2In the morning of the day of unloading
Target ExpertSend email notification to the Fermilab Fire Department
31 hour beforeNM4 Target Loading AreaAny Target Team memberNotify Fire Department via a Phone call

Stage the Target Loading:
Fill the target loading tub with LN2 at least 60-30 minutes ahead.  It will take 5 trips.  This should be done before calling the RSO, IH, ES&H or anyone else that is coming out to watch.  At this time check that the tools that are needed are laid out on the table, that the microwave and NMR tools are in the little plastic bag on the insert rack, that the insert handle is on the insert, that the screw driver for the lids is there.
  • Open the gHe backfill line regulator and valve D
  • Turn ON the ODH Fan for NM3
  • Check that there is a backup seal available.
4Before going into HallTarget Controls (Counting House)Target ExpertClose gate valve and GV-bypass for backfilling, ensure the fridge is no fuller than 20% otherwise boil it off with the annealing plates, ensure the target actuator position is in Middle position.
5Before going inHall Corridor into NM4Target Unloading TeamEnsure PPE for the occasion is used and that you sign the RWP (they check). 
6During ProcedureNM3 CaveTarget Loading TeamUnload insert.  Disconnect NMR cables and microwaves.  Put tools back in a little plastic bag. 
7After procedureTarget Controls (Counting House)Target ExpertAfter the target insert is unloaded, and once the fridge is closed, the Target Expert should keep the fridge in the Idle Mode.
8During ProcedureNM4 Target Loading AreaTarget Loading TeamTake photo of the insert cups, and also the bottle after unloading the material with the bottle label. 
9After procedureTarget Controls (Counting House)Target ExpertAfter procedure update the target inventory and post an FNAL elog about what material is in each target location.

Checklist for Unloading the insert without NH3/ND3

Item #LocationCheck Item
1Control room areaNotify the Target Expert, the run coordinator, and the FNAL RCT team
Is the FNAL RCT team available to access the cave with you? Discuss the work plan with everyone going to make the access.
Pickup NM3 and NM4 keys
2Control room areaClose the Gate Valve (GV), and the GV-Bypass valve
3Control room areaEnsure the target lifter is in the bottom position
4Control room areaPPE:
Cryo-gloves
PPE level 3 (Tyvex suit, gloves, shoe covers)
5Control room areaEnsure that the TO has a walkie-talkie to communicate and stay in the control room to monitor the system
6Control room areaHave you had a job briefing with everyone in the access team?
7Material handling stationAre the cart, collar+screws, insert-handle, and two nuts for the insert-handle ready?
8Material handling stationDo you have the wrench to disconnect the microwave? and also a 3/16 wrench in case NMR connectors are tight?
There should be a plastic bag (which contains those tools) hanging on the cart.
9On the way to NM3

Turn ON the ODH fans
OPEN the backfill gHe supply line (+ regulator to 4 psi + the valve D) on the cryoplatform
Turn ON the lights in the cave

10In-cave (before unloading)OPEN the two hand valves on the backfill panel to backfill the fridge. Ensure the pressure gauge is increasing to 0 psig (atmospheric pressure).
Confirm the gHe flow coming out from the 0.5 psig relief valve with your hand.
11
Disconnect the NMR cables and waveguide and place those away from the fridge with care.
12In-cave (before unloading)Do you have a banc-off flange, and an extra seal ready?
13In-cave (before unloading)Install the insert handle, and connect the hook to the insert's eyebolt.
14In-cave (before unloading)Disconnect the microwave wave-guide and NMR cable(s) and arrange them properly
15In-cave (before unloading)Have you checked the 0.5 psig relief valve's venting?
16In-cave (unloading)Unload the insert from the fridge
17In-cave (after unloading)Properly close the fridge using a banc-off flange and a seal
18In-cave (after unloading)Have you closed the two hand valves on the backfill panel?
Have you confirmed whether the blanc-off and its seal closed the fridge properly?
19On the way back from NM3

Have you turned OFF the lights in the cave?
Have you turned OFF the fan?
Have you CLOSED the backfill gHe supply line (+ the valve D) on the cryoplatform?



Checklist for Loading the insert without NH3/ND3

Item #LocationCheck Item
1Control room area

Notify the Target Expert, the run coordinator, and the FNAL RCT team
Is the FNAL RCT team available to access the cave with you? Discuss the work plan with everyone going to make the access.
Pickup NM3 and NM4 keys

2Control room areaClose the Gate Valve (GV), and the GV-Bypass valve
3Control room areaIs the fridge level below 20%? If not, bring it down below 20% using the annealing heat
4Control room areaEnsure the target lifter is in the bottom position
5Control room area

PPE:
Cryo-gloves
PPE level 3 (Tyvex suit, gloves, shoe covers)

6Control room areaEnsure that the TO has a walkie-talkie to communicate and stay in the control room to monitor the system
7Control room areaHave you had a job briefing with everyone in the access team?
8Material handling stationAre the insert, cart, collar+screws, insert-handle, and two nuts for the insert-handle ready?
9Material handling stationDo you have the wrench to disconnect the microwave? and also a 3/16 wrench in case NMR connectors are tight?
There should be a plastic bag (which contains those tools) hanging on the cart.
10On the way to NM3

Turn ON the ODH fans
OPEN the backfill gHe supply line (+ regulator to 4 psi + the valve D) on the cryoplatform
Turn ON the lights in the cave

11In-cave (before loading)Connect the hook to the insert's eyebolt
12In-cave (before loading)

OPEN the two hand valves on the backfill panel to backfill the fridge. Ensure the pressure gauge is increasing to 0 psig (atmospheric pressure).
Confirm the gHe flow coming out from the 0.5 psig relief valve with your hand.

13In-cave (before loading)Do you have an extra seal ready?
14In-cave (before loading)Have you checked the 0.5 psig relief valve's venting?


Wear cryo-gloves
15In-cave (before loading)Open the fridge banc-off flange and take off the seal.
16In-cave (loading)Load the insert
17In-cave (loading)Install the clamp with the seal, and after that you can remove the cryo-gloves, and connect NMR cables and/or microwave wave-guide
18
Remove the hook from the handle and also remove the insert handle from the insert, take it with you, and hang it on the cart along with the tools.
19In-cave (after loading)Have you closed the two hand valves on the backfill panel?
Have you confirmed whether the insert-top with the seal closed the fridge properly?
20On the way back from NM3

Have you turned OFF the lights in the cave?
Have you turned OFF the fan?
Have you CLOSED the backfill gHe supply line (+ the valve D) on the cryoplatform?




Checklist for Unloading the with NH3/ND3

Item #LocationCheck Item
1Control room areaNotify the Target Expert, the run coordinator, and the FNAL RCT team
Is the FNAL RCT team available to access the cave with you? Discuss the work plan with everyone going to make the access.
Pickup NM3 and NM4 keys
2Control room areaFill the LN2 tub, and blue transport dewar, and have some LN2 in the portable handheld dewar at the material handling station
3Control room areaClose the Gate Valve (GV), and the GV-Bypass valve
4Control room areaEnsure the target lifter is in the bottom position
5Control room areaPPE:
Cryo-gloves
PPE level 3 (Tyvex suit, gloves, shoe covers)
6Control room areaEnsure that the TO has a walkie-talkie to communicate and stay in the control room to monitor the system
7Control room areaHave you had a job briefing with everyone in the access team?
8Material handling stationEnsure the following things are ready
cart
collar+screws
insert-handle and two nuts
insert-handle
blue transport dewar with LN2
9Material handling stationDo you have the wrench to disconnect the microwave? and also a 3/16 wrench in case NMR connectors are tight?
There should be a plastic bag (which contains those tools) hanging on the cart.
10On the way to NM3

Turn ON the ODH fans
OPEN the backfill gHe supply line (+ regulator to 4 psi + the valve D) on the cryoplatform
Turn ON the lights in the cave

11At NM3

One person should go to the cave while the other person connecting the blue transfer dewar with LN2 to the hook at NM3.
The person in NM3 should wait until the blue transport dewar is taken into the cave by the person in the cave, and then go to the cave.

12In-cave (before unloading)

Place the blue transport dewar with LN2 on top of the magnet cryostat so you can quickly submerge the target cups as soon as the insert is taken out.

13In-cave (before unloading)OPEN the two hand valves on the backfill panel to backfill the fridge. Ensure the pressure gauge is increasing to 0 psig (atmospheric pressure).
Confirm the gHe flow coming out from the 0.5 psig relief valve with your hand.
14In-cave (before unloading)Disconnect the NMR cables and waveguide and place those away from the fridge with care.
15In-cave (before unloading)Do you have a banc-off flange, and an extra seal ready?
16In-cave (before unloading)Ensure that you have your cryo-gloves ready but don't wear them until you are done with this step and the next step
Install the insert handle, and connect the hook to the insert's eyebolt.
17In-cave (before unloading)Disconnect the microwave wave-guide and NMR cable(s) and arrange them properly
18In-cave (before unloading)Have you checked the 0.5 psig relief valve's venting?
19In-cave (before unloading)Wear cryo-gloves
20In-cave (unloading)Unload the insert from the fridge and submerge the target cups as soon as the insert is taken out.
21In-cave (after unloading)Properly close the fridge using a banc-off flange and the seal, and you can then remove the cryo-gloves
22In-cave (after unloading)Have you closed the two hand valves on the backfill panel?
Have you confirmed whether the blanc-off and its seal closed the fridge properly?
23In-cave (after unloading)Move the insert to NM3 carefully using the crane system and attach it to the cart with the collar and screws.
24On the way back from NM3

Turn OFF the lights in the cave
Turn OFF the fan
Have you CLOSED the backfill gHe supply line (+ regulator + valve D) on the cryoplatform?



Checklist for Loading the insert with NH3/ND3

Item #LocationCheck Item
1Control room area

Notify the Target Expert, the run coordinator, and the FNAL RCT team
Is the FNAL RCT team available to access the cave with you? Discuss the work plan with everyone going to make the access.
Pickup NM3 and NM4 keys

2Control room area,
Material handling station

Fill the LN2 tub, and blue transport dewar, and have some LN2 in the portable handheld dewar at the material handling station

3Control room areaClose the Gate Valve (GV), and the GV-Bypass valve
4Control room areaIs the fridge level below 20%? If not, bring it down below 20% using the annealing heat
5Control room areaEnsure the target lifter is in the bottom position
6Control room area

PPE:
Cryo-gloves
PPE level 3 (Tyvex suit, gloves, shoe covers)

7Control room areaEnsure that the TO has a walkie-talkie to communicate and stay in the control room to monitor the system
8Control room areaHave you had a job briefing with everyone in the access team?
9Material handling stationAre the insert, cart, collar+screws, insert-handle, and two nuts for the insert-handle ready?
10Material handling stationDo you have the wrench to disconnect the microwave? and also a 3/16 wrench in case NMR connectors are tight?
There should be a plastic bag (which contains those tools) hanging on the cart.
11Material handling station

Load the insert cups with the material, attach the blue transport dewar to the bottom of the insert,
and then hang the insert on the cart by installing the collar with screws

12On the way to NM3

Turn ON the ODH fans
OPEN the backfill gHe supply line (+ regulator to 4 psi + the valve D) on the cryoplatform
Turn ON the lights in the cave

13On the way to NM3Have you installed the insert handle, and connected the hook to the insert's eyebolt?
14In-cave (before loading)

OPEN the two hand valves on the backfill panel to backfill the fridge. Ensure the pressure gauge is increasing to 0 psig (atmospheric pressure).
Confirm the gHe flow coming out from the 0.5 psig relief valve with your hand.

15In-cave (before loading)Do you have an extra seal ready?
16In-cave (before loading)Have you checked the 0.5 psig relief valve's venting?
17
Wear cryo-gloves
18In-cave (before loading)Open the fridge banc-off flange and take off the seal.
19In-cave (loading)Carefully take the insert out from the blue transport dewar, and load the insert into the fridge
20In-cave (after loading)Install the clamp with the seal, and after that, you can remove the cryo-gloves, and connect NMR cables and/or microwave wave-guide, and also
connect the fridge sensor cable.
21In-cave (after loading)Remove the hook from the handle and also remove the insert handle from the insert, take it with you, and hang it on the cart along with the tools.
22In-cave (after loading)Attach the hook to the blue transport dewar which contains LN2 and carefully lower it down to NM3
23In-cave (after loading)Have you closed the two hand valves on the backfill panel?
Have you confirmed whether the insert-top with the seal closed the fridge properly?
24In-cave (after loading)Place the blue transport dewar on the cart and start moving the cart to NM4
25On the way back from NM3

Have you turned OFF the lights in the cave?
Have you turned OFF the fan?
Have you CLOSED the backfill gHe supply line (+ the valve D) on the cryoplatform?