Item #LocationCheck Item
1Control room area

Notify the Target Expert, the run coordinator, and the FNAL RCT team
Is the FNAL RCT team available to access the cave with you? Discuss the work plan with everyone going to make the access.
Pickup NM3 and NM4 keys

2Control room areaClose the Gate Valve (GV), and the GV-Bypass valve
3Control room areaIs the fridge level below 20%? If not, bring it down below 20% using the annealing heat
4Control room areaEnsure the target lifter is in the bottom position
5Control room area

PPE:
Cryo-gloves
PPE level 3 (Tyvex suit, gloves, shoe covers)

6Control room areaEnsure that the TO has a walkie-talkie to communicate and stay in the control room to monitor the system
7Control room areaHave you had a job briefing with everyone in the access team?
8Material handling stationAre the insert, cart, collar+screws, insert-handle, and two nuts for the insert-handle ready?
9Material handling stationDo you have the wrench to disconnect the microwave? and also a 3/16 wrench in case NMR connectors are tight?
There should be a plastic bag (which contains those tools) hanging on the cart.
10On the way to NM3

Turn ON the ODH fans
OPEN the backfill gHe supply line (+ regulator to 4 psi + the valve D) on the cryoplatform
Turn ON the lights in the cave

11In-cave (before loading)Connect the hook to the insert's eyebolt
12In-cave (before loading)

OPEN the two hand valves on the backfill panel to backfill the fridge. Ensure the pressure gauge is increasing to 0 psig (atmospheric pressure).
Confirm the gHe flow coming out from the 0.5 psig relief valve with your hand.

13In-cave (before loading)Do you have an extra seal ready?
14In-cave (before loading)Have you checked the 0.5 psig relief valve's venting?


Wear cryo-gloves
15In-cave (before loading)Open the fridge banc-off flange and take off the seal.
16In-cave (loading)Load the insert

In-cave (loading)Place Install the clamp with the seal and install the clamp, and after that you can remove the cryo-gloves, and connect NMR cables and/or microwave wave-guide
17In-cave (after loading)Have you closed the two hand valves on the backfill panel?
Have you confirmed whether the insert-top with the seal closed the fridge properly?
18On the way back from NM3

Have you turned OFF the lights in the cave?
Have you turned OFF the fan?
Have you CLOSED the backfill gHe supply line (+ the valve D) on the cryoplatform?

...

Item #LocationCheck Item
1Control room area

Notify the Target Expert, the run coordinator, and the FNAL RCT team
Is the FNAL RCT team available to access the cave with you? Discuss the work plan with everyone going to make the access.
Pickup NM3 and NM4 keys


Control room area,
Material handling station

Fill the LN2 tub, and blue transport dewar, and have some LN2 in the portable handheld dewar at the material handling station

2Control room areaClose the Gate Valve (GV), and the GV-Bypass valve
3Control room areaIs the fridge level below 20%? If not, bring it down below 20% using the annealing heat
4Control room areaEnsure the target lifter is in the bottom position
5Control room area

PPE:
Cryo-gloves
PPE level 3 (Tyvex suit, gloves, shoe covers)

6Control room areaEnsure that the TO has a walkie-talkie to communicate and stay in the control room to monitor the system
7Control room areaHave you had a job briefing with everyone in the access team?
8Material handling stationAre the insert, cart, collar+screws, insert-handle, and two nuts for the insert-handle ready?
9Material handling stationDo you have the wrench to disconnect the microwave? and also a 3/16 wrench in case NMR connectors are tight?
There should be a plastic bag (which contains those tools) hanging on the cart.


Load the insert cups with the material, attach the blue transport dewar to the bottom of the insert,
and then hang the insert on the cart by installing the collar with screws

10On the way to NM3

Turn ON the ODH fans
OPEN the backfill gHe supply line (+ regulator to 4 psi + the valve D) on the cryoplatform
Turn ON the lights in the cave

11On the way to NM3Have you installed the insert handle, and connected the hook to the insert's eyebolt?
12In-cave (before loading)

OPEN the two hand valves on the backfill panel to backfill the fridge. Ensure the pressure gauge is increasing to 0 psig (atmospheric pressure).
Confirm the gHe flow coming out from the 0.5 psig relief valve with your hand.

13In-cave (before loading)Do you have an extra seal ready?
14In-cave (before loading)Have you checked the 0.5 psig relief valve's venting?


Wear cryo-gloves
15In-cave (before loading)Open the fridge banc-off flange and take off the seal.
16In-cave (loading)Load the insert

In-cave (after loading)Install the clamp with the seal, and after that you can remove the cryo-gloves, and connect NMR cables and/or microwave wave-guide
17In-cave (after loading)Have you closed the two hand valves on the backfill panel?
Have you confirmed whether the insert-top with the seal closed the fridge properly?
18On the way back from NM3

Have you turned OFF the lights in the cave?
Have you turned OFF the fan?
Have you CLOSED the backfill gHe supply line (+ the valve D) on the cryoplatform?

...