QT System
- Check the purity of the outside gHe tanks, and regenerate/refill (max. pressure 145 psig)
- Clean up Dewars and the level-sensor tubes.
- Confirm all transfer lines' vacuum jackets are pumped down to 1 x 10^(-3) Torr in Pressure and < 1 x 10^-9 mbarL/s leak-rate.
- Leak-check all QT-system piping.
- Regenerate the purifier.
- Check F1, F2, F3 filters, oil filter, and oil level on HR3 and perform maintenance if required based on the scheduled maintenance.
- Check and confirm LCW supply to the cold-head compressors.
- Check the cold-head compressor pressure gauges and confirm 100 psi (IN) ~300 psi (OUT) (i.e. ~200 psi difference on both gauges in each compressor).
If not, pressurize the cold-head compressors using the HA.
Connecting Piping
Magnet