List of equipment, utilities, staffing and services need from Fermilab for target running and setup:
Inside Cave:
4 plugs/extensions for 10A 110-120 VAC 60 Hz standard US
Safety setup: lights rope for ODH and Magnetic field
Outside Cave:
500L liquid helium added to liquifier per month
3 He4-Gas K 2200psi (99.95%) bottles per week
Liquid Nitrogen supply for material handling: 100L/week
Deionized water (8 gallons + 1 gallon/week) for chillers used to cool the microwave generator
Clean power and conditioner/surge-protector for NMR
9 plugs/extensions for 10A 110-120 VAC 60 Hz standard US outlets
Set of 3 phase 220 V for pump stack
At least one 1 phase 220 V for Magnet
- Power Req: 200-240 V 50/60 Hz (prefer 208 V)
- Power consumption max: 3.3 kVA
Needs for setting up internal network at FNAL
Staffing:
One technician with specialized training 2 hour every day or every-other day (target changing and loading)