Activity (UBMI RBA)DurationStartDueNotes
UBI Development



UBI System Testing (Project Team)



UBI User Testing



UBI Move to Production2 weeks

MTP Checklist: 
UBI Go-Live



Activity (DI RBA)DurationStartDueNotes
Document Imaging Development


Rachel to complete Spreadsheet.
Document Imaging  System Testing (Project Team)


Rachel Sligar.

Rachel will identify scenarios - based on the spreadsheet.

Document Imaging  User Testing


TBD
Document Imaging  Move to Production2 weeks

MTP Checklist: 
Document Imaging  Go-Live




Activity - Workday RBA (HCM & FIN)DurationStartDueNotes
HCM App Upgrade Development



HCM App System Testing (Project Team)



HCM App User Testing



HCM App Move to Production2 weeks


HCM App Go-Live



FIN App Design



FIN App System Testing (Project Team)



FIN App User Testing



FIN App Move to Production



FIN App Go-Live








Onboarding Checklist: