Timelines 

Activity (UBI RBA)DurationStartDueNotes
UBI Development

March 4

Assume no integration with MyGroups.

Manual Setup by access team.

Extend: 

BP: 2/28-3/4

UBI UnitTesting (Project Team)
March 7March 8
UBI User Testing
March 9
Teresa to check with trainers.
UBI & DI Move to Production2 weeksMarch 21April 1MTP Checklist: 
UBI Go-Live
April 4

Activity (DI RBA)DurationStartDueNotes
Document Imaging Development


Rachel to complete Spreadsheet.

Extend: March 4 completion

BP: March 4 

Document Imaging  System Testing (Project Team)


Rachel Sligar.

Rachel will identify scenarios - based on the spreadsheet.

Document Imaging  User Testing


TBD
Document Imaging  Move to Production2 weeks

MTP Checklist: 
Document Imaging  Go-Live




Activity - Workday RBA (HCM & FIN)DurationStartDueNotes
HCM App Upgrade Development



HCM App System Testing (Project Team)



HCM App User Testing



HCM App Move to Production2 weeks


HCM App Go-Live



FIN App Design



FIN App System Testing (Project Team)



FIN App User Testing



FIN App Move to Production



FIN App Go-Live








Onboarding Checklist: