These activities will be the template for the Production cutover plan - so please update with any activities that are required for the Sandbox and Production migrations.

Add the following tasks:

  1. Remaining Development
    1. Teresa to enter 3 usability tickets (but not go-live critical)
      1. Message 'Please click 'OK'  - but the button says 'Approve'.  Please change to 'Please Click Approve'
      2. Add message 'your required training will appear as an action in your inbox'
      3. If submit on behalf of someone else - the test says it goes to the submitter's supervisor.  It should say 'the process will be approved by the subject's manager'.
      4. Assign to J/Diane.
  2. Go-Live on January 31
    1. 1/19: E2E Testing Complete
    2. Migrate to & Validate in Sandbox
      1. Week of 1/17: 
        1. E2E testing in UVA11
        2. Prod Prep:
          1. 1/13 Thurs: Extend Promotion to Production
          2. 1/17: Migrate BP and other config to SBX
          3. 1/20: Migrate BP and any other config to prod (and turn it off).
        3. 1/21 Fri: SBX Weekly Refresh
      2. 1/24 - 27 - Migrate to and Validate SBX
        1. Monday: Accenture Smoke Test BP (and other config) in SBX
        2. 1/24: Point Boomi QA to SBX  (note: once Boomi points to SBX, it will no longer point to UVA11).
          1. Boomi QA updates SIS QA.
        3. Tues-Wed: UVA Regression Test in Sandbox (will call Boomi QA - but not send to Boomi)
        4. Fri: SBX Refresh
      3. 1/28 - MTP
        1. 1/31 Go-Live
      4. DA?
IDTaskAssigned ToStatusStart DateDue DateNotes

Identify Proxy ListTeresaNot Started

Send list of testers that should be able to Proxy in SBX (for Regression test) to Kelli.

Obtain DA ExceptionTeresaNot Started1/121/19
1Update WD Extend Domain: Add Implementers - in ProductionLitaoCompleteThursday, January 13Friday, December 14

dependent on impl account

Security Request (securityRequest_drlmkt)

Litao added Implementers to the "Workday Extend" security domain in UVA11. Alternatively, this can be adding users to the "WD_XTND_SG" security group for Production.

Kelli - can we do this in Prod before our next migration to SBX?

1.1Add All User to "WQL for Extend" security domainLitao/KelliNot Started


1.1Create SIS & Data Steward Security Groups in ProdKelli/VenkatCompleteASAP

1.1Provide access to Production/SBXKelli/VenkatComplete

Kelli working with Chris and Stewart re: NetBadge for SSO.
1.1Task: Manage Extend Apps with Model Components. LitaoNot StartedThursday, January 13Thursday, January 17dependent on impl account
1.1Add assignees to SIS & Data Steward Security Groups in Production/SBXMichaelNot StartedThursday, January 13Friday, January 21

MN - loaded with EIB 12/8/21.  This EIB will alao work to assign users in Prod.

Kelli has added the security groups to Prod (and therefore copied into UVA11).  


Add SIS and Data Steward groups to Personal Data Other IDs domain, view onlyMichael/KelliComplete


1.1Promote Extend Application to Production/SBXLitaoNot StartedThursday, January 13Thursday, January 13

Dependent on UVA7 access.

Update url links in scripts (linkRoute.script).

1.2Calculated fieldsLitaoNot StartedMonday, January 17Friday, January 21

Used OX to migrate.  

Litao: There were a couple of calculated fields the pages use. Perhaps next migration this line will be assigned to Extend team.

1.2Condition rules (BP step conditions)Michael/Matt (with Diane and J)Not StartedMonday, January 17Friday, January 21

Used OX to migrate the full BP.  Worked through Ref IDs and various other sync issues with Diane, Jay and Matt 12/13/21.  

Who will do the BP Admin updates in Prod?  Teresa will check with Syed (it will not be Michael and Matt).

1.2Documents for Doc Distribution stepsMichael/Matt (with Diane and J)Not StartedMonday, January 17Friday, January 21

** Note, the documents came over with the BP successfully but we need to remember to update the FERPA course WD link in the document distribution instructions relative to the target tenant. 


Used OX to migrate the full BP.  Worked through Ref IDs and various other sync issues with Diane, Jay and Matt 12/13/21.  

1.2To-Do'sMichael/Matt (with Diane and J)Not StartedMonday, January 17Friday, January 21Used OX to migrate the full BP.  Worked through Ref IDs and various other sync issues with Diane, Jay and Matt 12/13/21.  
1.2NotificationsMichael/Matt (with Diane and J)Not StartedMonday, January 17Friday, January 21Used OX to migrate the full BP.  Worked through Ref IDs and various other sync issues with Diane, Jay and Matt 12/13/21.  
1.2Kelli to update segmented security.  KelliNot StartedMonday, January 17Friday, January 21See UVA-224.
1.2Custom TasksSimon and CoryNot StartedMonday, January 17Friday, January 21Do only in SBX and only do in Production when going live
1.2Create Client Credential Mapping in UVA11LitaoNot Started

Depedencies - ISU is available

Important for Boomi connection to WD.

2Smoke Test ConfigMichael/MattNot StartedMonday, January 17Friday, January 21I ran a full request for Hattie Agee with 7 requested roles across all modules and then added an 8th by a reviewer.  No errors, routed through 46 steps and 19 review or approval proxy.
2Smoke Test ExtendLitaoNot StartedMonday, January 17Friday, January 21
3Setup ISU for Boomi in Production/SBXSri/KelliNot StartedMonday, January 17Friday, January 21

Ensure the Boomi ISU password ‘change pw next login’ is unchecked.  This is a lesson learned from UVA11 migration - Boomi team was notable to successfully run the Add/Remove Roles RaaS report until this was unchecked.

3Setup ISU for Orchestration in Production/SBXKelli/VenkatNot StartedMonday, January 17Friday, January 21
3Setup External Client Cred StoreKelli/VenkatNot StartedMonday, January 17Friday, January 21Depends on ISU for Orchestration
4Custom Dashboards (Admin Requests and My Requests)Extend TBDNot StartedMonday, January 17Friday, January 21

Dependent on Custom Tasks.

Ensure it is set to 'Required' for SIS Reviewers.

Do only in SBX and only do in Production when going live

4Migrate Boomi Integrations and SIS updates to PROD and point to PRODKaren/VinnieNot StartedMonday, January 17

Not dependent on any Extend or Config migration.
Boomi/SIS will stay in QA and will point to future tenants.
MTP - will migrate to Prod

Boomi integrations have been moved to QA - Karen and Vinnie to attend office hours to complete.

12/15 - Pending - Add Removals smoke testing

4Validate Boomi integrations and SIS updates in QAKaren/VinnieNot StartedMonday, January 17
Dependent on Boomi ISU , RAAS Report Access
4Apply permissions and Users to Disposition Lists - in Production/SBXKelli/MichaelIn ProgressMonday, January 17Friday, January 21

Security groups are in Prod (and copied).

Michael added the people to the groups.

4Update Security Group Reference ids in UVA11.MichaelComplete

Confirm for SBX/Prod - this should be fine, but include in validation to confirm. 

Already complete in Production (UVA11 and Prod are in sync).   

4Migrate Reports to Production/SBXSriNot StartedMonday, January 17Friday, January 21
4Confirm Report Ownership to Boomi ISUSriNot StartedMonday, January 17Friday, January 21Dependent on ISU for Boomi
4Verify/Update Proxy and Security for SIS TeamKelli/VenkatNot StartedMonday, January 17Friday, January 21Updated all I was aware of, which would include the current team. 
5Unhide the SIS details to the Announcements pageKelliNot StartedMonday, January 24
Entered in UVA11 and Production, though is currently hidden in production. 
5Confirm Smoke Test complete - Ready for UVA ValidationLeslieNot StartedMonday, January 24Monday, January 2412/16 - Litao and Michael confirmed smoke testing success.  REady for UVA Validation.
5Regression Test in SBXSIS TeamNot StartedTuesday, January 25

Wednesday, January 26

Identify what is needed - will need an exemption due to ABO migration timing.
6Configure Custom Task and Dashboard in ProductionKelli/MichaelNot StartedMonday, January 31

6Project Team Check-in Teresa/LeslieNot StartedMonday, January 31

6Announce SIS App is liveTeresaNot StartedMonday, January 31