The subunits of the lifter system

  1. Lifter mechanical+Electrical setup (in the target cave)
  2. Lifter control box (Slow controls rack)
  3. Lifter ADC Box (Slow controls rack)
  4. Lifter monitoring box (Control room)

Details of each unit

  • Lifter mechanical setup

    QtyDescriptionManufacturerPart number
    7Limit switchHoneywell311SM6-T
    2String Potentiometer TE connectivityPT1A-15-UP-10K-C25
    1stepper motor Applied Motion Products, Inc.HT23-600
    2Right-Angle Gear DriveAndantex USA
    2Screw JackDuff-Norton

    The seven(7) position switches are labeled as in the following image. The Upper Limit and the Lower Limit are 


  • Lifter Control box

The attached ORC document describes the details of the lifter control box ORC-1865_ORC_Lifter Control System.pdf



The complete lifter system diagram 










After each gearing stage  5000 motor steps = 1" travel 

This is the report prepared by the designer of the lifter   E1039 Target Frame and Lifter Final Report.pdf 

This is the ORC document which covers the electrical wiring in the lifter setup Lifter Electrical ORC.pdf