- The insulation vacuum of the magnet has been pumped down for multiple days and the vacuum level is below 8x10−6 Torr
- The U-Tube connection between the magnet and the fridge is installed and pumped down to below 1x10−3 Torr
- The QT transfer line and all 3 stingers, Dewars and cold boxes have been pumped down to below 1x10−3 Torr
- QT transfer line stinger is installed on the north riser of the magnet
- Both QT dewars are full
- Magnet is backfilled and magnet pressure is above the atmosphere
- Magnet shield is filled with LN2: If not, then follow Filling Magnet Shield with LN2
- Purity of the system (after roots, outside tank, inlet of HR3, magnet return) is close (within 0.03%) to to reference (100.43%)
...