Checklist:
- On QT-HMI ODH page ensure LL-106-N Shows < 75%. Ensure the level probe readout in the magnet power supply rack (cryoplatform) is ON, and the output from it to the PLC is ENABLE. Check with the Target Expert on Shift to find the level probe readout statusis reading the shield level and that it shows < 75%.
- PT-106-N is below 15 psig (pressures above ~17.08 psig are not going to be read so we are blind above this value. Discussions about increasing the readout range will be done after the holidaysshield relieves at 35 psi, pay attention to not exceed that value).
- PT-110-N reads a value between 20psig-65psig.
- Ensure EV-200-N is closed. It may have been left open earlier since the purifier was filled. If it is left open, then leave it open and then close it after Step #2 below.
- Ensure VNFA on the purifier overview LN2 is CLOSED.
- LN2 tank (Tank #54) outside has > 20 inwc level.
- HCV13 (hand-valve at the tank) is CRACKED OPEN to about 1/2 turns from the fully closed position (on 12/22/2023 we decided to leave it at this position).
- Note down the start time and the initial level for the elog entry.
...