  1. Pump and purge the IVC with gN2 (at least 5 times). Make sure the pop-off valve on the magnet IVC is closed after each pump-purge cycle, and leave it closed.
  2. Check the LN2 level in the outside tank. Ask Jordan (FNAL) to order a refill for the outside LN2 tank.
  3. Pump-purge the separator space, and at the end of pump-purge cycles, keep the separator pump-out line pressurized and close the hand-valve in the cave.
  4. Pump-purge magnet space with measuring purity at each cycle.
  5. Pump-purge the fridge.
  6. Unscrew run, bypass valves (in the fridge), and take them out.
    > Blow gHe through it.
    > Spray dry lube
  7. Warm gHe circulation tests.
  8. Ensure both QT Dewars are full (~200L).