Front Penetration (55 ft to cryoplatform) : All other cabling

 

West Penetration

--------------------------------(Cryo)---------------------------------------------------------------------------------------------------------------

Cryogenics

Vapor return for QT transferline (0.5 inch SS/copper line with 0.5-1 inch foam)

...

He gas (1/8 hose HDPE for gas lines for backfilling fridge)

 

 (

Electrical

...

SuperConducting Magnet Power:

...

Shim power (two 7 mm cable)

 

 

 

Top ceiling Penetration

-----------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

Magnet boil off exhaust (25 mm flex hose with 0.5-1 inch foam) back to QT T-ed outside of cave to Quench relief outside of Hall

LN2 port exhaust (25 mm flex hose with 0.5-1 inch foam) should have a fan pulling vapor

 

 

 

East Penetration

(less than 47ft from target to cryo-platform)

---------------------------------------

NMR lines <30 mm dim collection of multiple coax (highly length sensitive)

------------------------------------------------------------------------------------------------------

NMR lines - Highly Length Sensitive

    Quantity:

    Diameter (each):

    Diameter (Collective): < 30mm

    Part Number:

 

EIP Microwave Frequency Counter (Gorex):

...

    Diameter: 0.210"

    Length:

 

Top Front-East Opening

(shortest length is about 55ft from target to cryo-platform)

--------------------------------------------------------------------------------------------------------------------------------------------

...