Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
No PII should be placed in this Project Portal.  Any such data should be placed in the designated sFTP location.  Please contact your PM with questions.

Timelines 

Activity (UBI RBA)DurationStartDueNotes
UBI Development

March 4

Assume no integration with MyGroups.

Manual Setup by access team.

Extend: 

BP: 2/28-3/4

UBI UnitTesting (Project Team)
March 7March 8
UBI User Testing
March 9
Teresa to check with trainers.
UBI & DI Move to Production2 weeksMarch 21April 1MTP Checklist: 
UBI Go-Live
April 4


Activity (DI RBA)DurationStartDueNotes
Document Imaging Development


Rachel to complete Spreadsheet.

Extend: March 4 completion

BP: March 4 

Document Imaging  System Testing (Project Team)


Rachel Sligar.

Rachel will identify scenarios - based on the spreadsheet.

Document Imaging  User Testing


TBD
Document Imaging  Move to Production2 weeks

MTP Checklist: 
Document Imaging  Go-Live




Activity - Workday RBA (HCM & FIN)DurationStartDueNotes
HCM App Upgrade Development



HCM App System Testing (Project Team)



HCM App User Testing



HCM App Move to Production2 weeks


HCM App Go-Live



FIN App Design



FIN App System Testing (Project Team)



FIN App User Testing



FIN App Move to Production



FIN App Go-Live








Onboarding Checklist: