These activities will be the template for the Production cutover plan - so please update with any activities that are required for the Sandbox and Production migrations.

Timeline:

  1. Prepare in Sandbox (2-ish days):
    1. Update condition rules (38)
    2. Update notifications
    3. Create role based group
    4. EIB to make assignments (Billy sent current list to Kelli)
    5. Create Adaptive User Based Group
  2. Adaptive team to identify scenarios:
    1. Remove everyone from user-based group - use EIB to add them to new role-based group - Run Sync - Adaptive team to confirm 
    2. Add new users
    3. Remove users
  3. Have a call where we implement in SBX (early in the week)
    1. Adaptive team to test in SBX
    2. Sec Admin to test/validate in SBX
  4. Have a call where we implement in Prod (early in the week)
    1. Full team to validate and enter Test Transaction
    2. Communicate 
    3. MTP:
      1. Week of 9/19: Implement & Test in Sandbox
        1. 9/19-20: Matt to configure/Implement in SBX
        2. 9/21-22: Adaptive & RBA Test/Validate
      2. Week of 9/26: Migrate/Implement & confirm in Prod
        1. 9/26: Matt to Migrate BP, Manually create groups, run EIB in Prod (finish by 1pm)
        2.  9/26 1pm ET: Meeting on 9/26 with Michele and Swapnil for final config and validation
        3. 9/27 8am - Go-Live


TaskAssigned ToStatusStart DateDue DateNotes
Identify Proxy ListTeresaComplete

Matt already has proxy in SBX.  Assume this is sufficient (per prior testing sessions).

Provide access to Production/SBXKelli/VenkatComplete

All project team members have access
Identify CommunicationsTeresa/MichelleIn ProgressThursday 9/15Friday 9/16


Identify plan for open Salesforce TicketsTeresa/MicheleIn ProgressThursday 9/15Friday 9/16

Update Configuration in Sandbox:

  1. Update condition rules (38)
  2. Update notifications
  3. Create role based group
  4. Create Adaptive User Based Group
MattCompleteMonday 9/19Friday 9/23


Provide Adaptive access to ImplementersTBDTBD


Create Role Assignee EIBMattCompleteThursday 9/15Tuesday 9/20Billy sent the list of current assignees to Matt.
Identify Test scenarios to Regression Test TeresaCompleteThursday 9/15Tuesday 9/20
  1. Remove everyone from user-based group - use EIB to add them to new role-based group - Run Sync - Adaptive team to confirm 
  2. Submit a single test
  3. Removal

Testing session scheduled for 9/27

Smoke Test in SBXMattCompleteThursday 9/22Monday 9/26


Regression Test in SBX

FST & HCM Team

CompleteTuesday 9/27

Teresa to schedule.

Testing session scheduled for 9/27

Update Notifications in SBX

  1. On Completion
  2. On Removal
MattIn Progress9/279/28
Compare the list of users in the Role-based and User Based Groups to confirm.MattIn Progress9/279/28
Load the Role Assignee EIB in SBXMatt & TeamCompleteTuesday 9/20

Provide updated list of Prod usersBillyNot StartedDay before go-live
255 users as of 9/27 (8-9 more than initial list)
Matt to migrate and manually update config in PRODMattNot Started9/28 morning

Advance: Migrate BP, Manually create groups, run EIB

Together: Update report, Domain Changes to switch from UB to RB

HCM & FST: Final Config and Send Test transaction in PROD

Team


Not Started

  1. Meeting TBD:  with Michele and Swapnil
  2. Add adaptive group to custom report that populates the form (so people can select it)
  3. Update domain to remove the user based group
  4. Test case: Tony Hash is initiator and Carol Temerson is the approver
Adaptive Go-LIveTeresaNot Started


Any communications for Web Site updates?

Teresa

Not Started

9/19/2022  - Met with Michele Gregory and Bill Mak on Friday, they will handle the communications and can post on the Adaptive site and Michele will reach out to the FST Communications (Brandi) team as well.   There is one big open SF ticket for Phil Pollick which is in progress, that they will grandfather.    Note training is REQUIRED for Adaptive 