o Connect roots pumps to H20 + P&ID for roots water system + P&ID for roots vacuum system (do we have all the instruments listed?) o ORC documentation for the roots o Populate target control racks with equipment + List of cables to-from target to rack + List of cables to-from control room (cables to be pulled through penetrations) + Plan for target rack(s) in the control room (what goes where, power requirements, etc) + ORC documentation for custom electronics in racks o Cable tray installation (east side of shielding) o Cable tray installation (west side of shielding) o RF cooling loop plans (P&ID) o Pneumatic system P&ID o Electrical isolation of remaining target services (equivalent is a plan for earthing the system).