Do Immediately | Additional Information |
---|
Fridge sensors | 1KOhm Ruthenium Oxide |
Determine and measure true path for all cables coming from target cave | Front Penetration → Racks on Cryo platform → Counting House Side Penetration → Racks on Cryo platform → Counting House |
Liquid Helium Level Probe mounting clips | Being made at UVa - 7/17/19 |
Replace Black BUNA-N O-rings | Measure existing O-rings and find PTFE (Teflon) equivalents - Run/bypass valves
- Shell to magnet
- Shell to turret
- Turret to fridge
- Electrical feedthroughs
- Bottom can
- Red pop-off valve
|
Make and test indium seal on shell/nose | |
| |
Buy a flaring tool for copper tubing | |
Assemble and test microwave system | Needs to be shipped from UVa - 7/17/19 Borrow gore cable from UVa Need waveguide too |
Get Liverpool NMR Q-meter (and ancillary equipment) from LANL | |
Once EIO arrives, connect EIP and test air core cable | |
Setup sensors on stick | Check with lakeshore |
Stink test in the target loading area | with "special" spray |
Setup and test manometer | |
Setup external magnet sensors | |
Shim Microwave actuator bushings for hard stop and top target | |
Things to do when not working on the immediate things | Additional Information |
---|
| |
Setup Target Rack | Stepper motor drives and power supplies ADC for position readbacks Microwave EIP Lakeshore 218 x2 Level Probe Readout Turbo readout and Controller IV gauge readout Teledyne Hastings readout 4He & 3He manometers Possibly Microwave Power Supply Target Insert Lakeshore Fridge Lakeshore External Magnet Lakeshore |
Get hoses for microwave (EIO) | Either hard plastic or rubber |
Target Controls Computer | Josh will find it |
All cabling from target to racks and counting house | need lengths and to order cables |
setup target operator station | |
setup target loading station | |
Finalize NMR | testing still needed |
Target handler and alarm system | |
Setup NMR VI | |
Annealing controls | |
Setup and test Main Gate Valve | |
Test Air-core cable with EIP/microwave | |
Setup Insert and leak check and electronics check, sensors, coils, SMA | |
Setup Nuc and oscilloscope and PDP | |
Setup Roots stack controller and power | |
Get some plastic tubs and foam dewars | |