You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 18 Next »

The top mounting plate can be positioned whenever the techs come to do it. 
The machining and materials from UVA have arrived and are ready.  This
includes the bottom target tri-winged frame and the new aluminum feet
holders.  The threaded feet are also finished from FNAL.  The dowel pins
should be done soon.  After this the lifter frame should go in and then
the magnet can in principle go into position.  In order for us to be ready
for that we want new PTFE seals which are more radiation resistant.  We
need to clean and prep the magnet and can, and to do the doc survey.
1.) Survey on doc with full system open (no nose, no nitrogen shield, no
beam windows).  Survey the magnet aperture, the target insert along X
only, and the outside fiducials (can and top flange).  The primary goal of
this survey is to generate fiducials on the can and top flange to help
align when going into position in the cave.
Do ImmediatelyAdditional Information

Fridge sensors

1KOhm Ruthenium Oxide
Determine and measure true path for all cables coming from target cave and order all cable needed

Front Penetration → Racks on Cryo platform → Counting House

Side Penetration → Racks on Cryo platform → Counting House
Liquid Helium Level Probe mounting clipsBeing made at UVa - 7/17/19
Replace Black BUNA-N O-rings

Measure existing O-rings and find PTFE (Teflon) equivalents

  • Run/bypass valves
  • Shell to magnet
  • Shell to turret
  • Turret to fridge
  • Electrical feedthroughs
  • Bottom can
  • Red pop-off valve

Make and test indium seal on shell/nose also setup safety walk through for testing stand vacuum vessel

Setup Operational Readiness Clearance (through Rick)
After replacing seals setup safety walk through withSetup Operational Readiness Clearance (through Rick)
Buy a flaring tool for copper tubing 
Assemble and test microwave system

Needs to be shipped from UVa - 7/17/19

Borrow gore cable from UVa

Need waveguide too

Get Liverpool NMR Q-meter (and ancillary equipment) from LANL 
Once EIO arrives, connect EIP and test air core cable 
Setup sensors on stickCheck with lakeshore
Stink test in the target loading areawith "special" spray
Setup and test manometer 
Setup external magnet sensors with data going into slow controls data stream 
Shim Microwave actuator bushings for hard stop and top target. Microwave table and magnet should be in place and use the information from initial survey to measure 
Things to do when not working on the immediate thingsAdditional Information
  
Setup Target Rack

Stepper motor drives and power supplies

ADC for position readbacks

Microwave EIP

Lakeshore 218 x2

Level Probe Readout

Turbo readout and Controller

IV gauge readout

Teledyne Hastings readout

4He & 3He manometers

Possibly Microwave Power Supply

Target Insert Lakeshore

Fridge Lakeshore

External Magnet Lakeshore

 

Get hoses for microwave (EIO)Either hard plastic or rubber
Target Controls ComputerJosh will find it
All cabling from target to racks and counting houseneed lengths and to order cables
setup target operator station 
setup target loading station 
Finalize NMRtesting still needed
Target handler and alarm system 
Setup NMR VI 
Annealing controls 
Setup and test Main Gate Valve 
Test Air-core cable with EIP/microwave 
Setup Insert and leak check and electronics check, sensors, coils, SMA 
Setup Nuc and oscilloscope and PDP 
Setup Roots stack controller and power 
Get some plastic tubs and foam dewars 

 

For SpinQuest it will be difficult to get the positioning of the target
perfectly aligned with the beam.  This is because all fiducials that we
can get while the system is warm and open will change once we are running
with liquid helium.  We have X, Y positioning measured from averaged
vertex reconstruction but this takes at least 1 month of data to produce,
and this will only give the mean with a very large variance.  This means
we need to get the information we need from the survey and the final set
of surveys will need to contain some cold target information.  The
precision in the target cell to beamline positioning needs to be good to
mitigate large absolute errors while running.   This is estimated to be on
the sub-millimeter level (based on simulations being confirmed).  There
are several factors that can lead to false asymmetries relating to this
precision.  There can be a bias produced in the detector if there the beam
is off center.  There can be less polarized scattering if the beam is not
aligned and missing part of the target (beam profile dependent, also being
checked).  There can be greater scattering off the aluminum ladder on one
side as compared to the other.  Most of these manifest from X being off
but if Y is off over 1 mm then the same issues start to manifest with the
ladder as well but this may not result in false asymmetry and only result
in additional heat load to the coils.

During our discussions with the survey crew it was suggested to install
transparent windows so we could do an optical survey on the magnet and
target cells while cold.  This would be great to do but I do not think
this is possible at FNAL.  I don't believe we would ever pass a safety
review to do that.  The next best option is to do surveys using liquid
nitrogen.  We could calculate the level of contraction for both LN2 and
LHe.  We can then measure the contraction during an open system survey
with LN2 in the magnet and in a nose with a window on it.  The set of
survey would go like this:

1.) Survey on doc with fully open system (no nose, no nitrogen shield, no
beam windows).  Survey the magnet aperture, the target insert along X
only, and the outside fiducials (can and top flange).  The primary goal of
this survey is to generate fiducials on the can and top flange to help
align when going into position in the cave.  This part of the survey should
be able to be measured at less than 0.1 mm.  The fiducial on the can is meant
to use to align the top and bottom to our best precision.  The drawings indicate
a change of 4.5 mm up when cold.  The tolerance of these drawings is 0.5 mm.

2.) Survey in cave using LN2 in nose and magnet.  This would be a partly
open survey with a special nose put on with transparent windows on either
side for optical survey.  The nitrogen shield and beam widows on the
vacuum are left off for this.  This survey in the cave will be of the
magnet aperture, the target insert along X, Y, Z, and the outside
fiducials (can and top flange and reference locations in the cave). 
Crosshairs will be use in the front and back of the target cell to help
determine degree of twisting in the cell.  Cross hairs in the can windows
can also be use to set the rotational alignment of the can.  The target
insert carbon fiber is not expected to contract very much but the aluminum
ladder can.  The primary goal of this survey is to compare to calculations
of contraction and measure positioning of target cell with respects to
magnet aperture and also with respect to the beamline.  There should be a
hard stop setup on the actuator that positions the top target exactly in
the beam line (to test repeatability of the string potentiometer and gears).
We also need to take the stick out and few times and test the scale of 
deviation in reproducibility in target cell shifts and bends.
This will take two surveys to do since we will need to machine the piece for
this hard stop after this first cold survey measurement.  In order to do this
the actuator and motor should be installed so we can move up and down with
reasonable repeatability.  This repeatability can also be tested during this survey.

3.) Put in hard stops and re-survey.  This will be adding a shim to the
hard stop that already exists.  Here we can have the goal of .25 mm target
centering in X,Y and measure a set of cells using cross hairs in Z.

4.) An X-ray survey while cold would be the next step if possible.  We may
not needed it if we achieve good results from the first 3.  It may also be
possible to use phosphine graph paper to check beam position on a special
target insert without depending on the magnet or nose having LHe in them.
Or use something that discolors or burns in the beam so we can make an

insert that will be use over the experiment to check position.

  • No labels