Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Standby mode
    • We need to determine the setting for fridge valves and gate-valve bypass that allows us to keep things cold but uses the least amount of liquid helium as possible.
    • The place to start for this study is to overfill the nose to the top of the heat exchanger, crack the run valve, and open the gate-valve bypass just a little so you get something like ~1 slm going through the separator flow.
    • The pressure in the nose will build a bit which is what you want.  You want to let it rise to maybe a few hundred Torr and find out what the optimal storage temp/flow is.
    • This is the mode we should keep the system in when we are not doing something with the fridge.
    • It's also possible to let the helium in the nose boil off and just keep the separator cold.  This would be the recommended state if we do not use the fridge for many days.  However, every time we let the nose empty we will have to cool it down again which is inefficient both in terms of time and helium.
  • TE mode
    • There is a range of different temperatures we might want to perform TE measurements at.  We need to learn what run valve and gate-valve bypass setting correspond to what temperature of interest.
    • We need the backing pump running with the gate-valve bypass cracked with the nose being filled by the run valve but at the least amount open to hold the temperature in the nose fixed.  We want to be able to do this for various temperatures (1.7K, 2K, 2.5, 3K...).
    • The run valve setting should be fixed so that it's not introducing helium at a different temperature than the nose reservoir at a fluctuating rate.
    • The best temperature sensor we have at the moment is the 100 Torr red brick Baratron.  Use that helium vapor pressure to determine the temperature of the nose.
    • This could be uniquely challenging because of the way the nose fills (no fill tube just sprays).  The time required for the target to thermalize is longer for lower temperatures.  You would need to wait at least 3 times the t1 (longitudinal relaxation rate).
    • As a starting point, we should demonstrate that we can hold a fixed temperature in the nose for at least 30 minutes at these various temperatures.
  • Operations mode
    • Operations means that the microwave is running and the beam will be coming once every minute for 4.4s.  This is an additional heat load to the system.  Here we want our maximum cooling power and lowest temperature possible.
    • All roots are running and the run valve is open so we are seeing about 20 slm on the Main Flow.  The run valve operating on a PID on Main Flow may be helpful here.
    • We should demonstrate the feasibility of this mode over a long period of time.

Procedure for Filling the Fridge with LHe

The fridge is supposed to have no LHe at the beginning.  The filling should be done once per two days.  You can/should use this preset page to monitor the key parameters.

  1. Change the separator flow to 20 SLM (from 7 SLM usually).

  2. Wait for 1.5-2.0 hours.
  3. Change the separator flow to 25 SLM.
  4. Change the setting of the gate-valve bypass as follows:
    1. The auto control is disabled.
    2. The absolute valve position is 0.1 turns or larger.
  5. Enable the interlock with Heat-Ex Top (on Fridge_Valve_Main.vi).
  6. Open the bypass valve at 2.0 turns.  Confirm that the fridge return flow goes up.

  7. Go into the cave to fully open the gate-valve bypass.
  8. Open the bypass valve at 3.0 turns.
  9. Change the separator flow to 30 SLM.
  10. Wait until the Ann-Plate Top resistor goes up to 1400 Ohm, which indicates that the liquid started accumulating.

    1. It usually takes 30 minutes from step #3.  If it takes longer than 40 minutes, search for unexpected conditions.
  11. Wait until the nose LHe level reaches 100%.
    1. It usually takes 15 minutes from the previous step.
  12. Wait until the Heat-Ex Bottom resistor goes down from 1400 Ohm and then up.
    1. It usually takes 10 minutes from the previous step.
  13. Wait until the Heat-Ex Top resistor goes up to 1400 Ohm, which indicates that the liquid is as high as Heat-Ex Top.

    1. It usually takes 10 minutes from the previous step.
  14. Close the bypass valve.

    1. The software interlock sets it at 0.5 turns automatically.
    2. You then set it at 0.0 turns manually.
  15. Change the separator flow to 7 SLM.

  16. Change the setting of the gate-valve bypass as follows:
    1. The set point for the auto control is 20 Torr.
    2. The auto control is enabled.
  17. Make an elog entry to record the time and the mount of this filling.


Fridge Related Procedures

1. Fridge Fill Procedure


Old Procedure for Filling the Fridge with LHe (Until November 2023)

Expand

The latest official procedure is posted on DocDB 10375.  The procedure described below is expected to replace (improve) it in future.

The fridge is supposed to have no LHe at the beginning.  The filling should be done once per two days.  You can/should use this preset page to monitor the key parameters.

  1. Change the separator flow to 20 SLM (from 7 SLM usually).

  2. Wait for 1.5-2.0 hours.
  3. Change the separator flow to 25 SLM.
  4. Open the bypass valve at 2.0 turns.  Confirm that the fridge return flow goes up.

  5. Go into the cave to fully open the gate-valve bypass.
  6. Open the bypass valve at 3.0 turns.
  7. Change the separator flow to 30 SLM.
  8. Wait until the Ann-Plate Top resistor goes up to 1400 Ohm, which indicates that the liquid started accumulating.

    1. It usually takes 30 minutes from step #3.  If it takes longer than 40 minutes, search for unexpected conditions.
  9. Wait until the nose LHe level reaches 100%.
    1. It usually takes 15 minutes from the previous step.
  10. Wait until the Heat-Ex Bottom resistor goes down from 1400 Ohm and then up.
    1. It usually takes 10 minutes from the previous step.
  11. Wait until the Heat-Ex Top resistor goes up to 1400 Ohm, which indicates that the liquid is as high as Heat-Ex Top.

    1. It usually takes 10 minutes from the previous step.
  12. Close the bypass valve.

    1. The software interlock (on the Cryo Control Panel) first sets it at 0.5 turns automatically.
    2. You then set it at 0.0 turns manually.
  13. Change the separator flow to 7 SLM.

  14. Go into the cave to partially close the gate-valve bypass.
    1. Move the valve handle until it gently hits its stopper, where a spacer is attached to the stopper so that the gate-valve bypass is closed only partially.
  15. Make an elog entry to record the time and the mount of this filling.

Procedure for Filling the Fridge with LHe to Start the "Standby" Mode

...