Preparation:
- About ~3 hours before the fill, select the Dewar (A or B) to perform the fill (based on the current available LHe levels).
- Set the “Dewar Set Pressure” to 3 psi on the QT HMI Liquefier A/B screen’s “Settings” page.
- Check the outside gHe pressure and make sure it is below 90 psi. If it's equal, near, or above, then relieve its pressure down to ~80 psi.
- Check The cave for insulation on cryostat with fans.
- Open the Connect to the “Cryo Control Panel” on the cryo-computer, or connect to the Cryo Control Computer (via VNC: see Polarized Target System for SpinQuest at FNAL for the instructions)
- Monitoring screens during the fill
a) "Transfer-Line Cool Down" : During the pre-cool
b) "LHe Transfer": During the fill
...