The following procedures suppose that you use the remote control interface (i.e. Cryo Control Panel; CCP).  When you use the front panel of the magnet PS, some button operations are different.

Things to-do

  1. We should get the information of Clamped/Reate-Limit/Quench from the Mercury-iPS to the VI
  2. We need to be able to ramp-down 0A with 0.5A/m rate, so there should be a preset for that.
  3. Need a manual override in the VI.
  4. We need a power-indicator on the shim power supply. These are the shim-coil-power indicators.
  5. We need a field indicator in the cave.

...

Precautions

...

  • The magnet LHe level is so high (>20%??) that LHe remains even if soft quench happens.
  • A time to ramp up/down the magnet should be planned in advance, since it takes at least 1.5 hours.
  • You should remember that any deviation from the standard procedure might cause quench.
  • You are expected to know what should happen at each step and confirm that it happened.  You had better go through this procedure with another person who has already carried it out.
  • You should search for any indication of quench during the operations, such as error messages on the magnet PS, sudden changes of Tank B, Coil T, Coil B, the magnet pressure, etc.

To Ramp Up

  1. Confirm that the shim PS is powered ON (if you can go in the hall).
  2. Press "To Zero", to confirm that CCP can communicate with the magnet PS.
  3. Press the Toggle button of the main switch heater.  It turns on the main switch heater and also the two shim switch heaters.
    1. When you use the PS front panel, you have to press additionally the two buttons of the shim switch heaters on CCP, to turn them on.
  4. Confirm that the two LEDs on the shim PS are ON (if you can go into the hall).
  5. Set "2 A/m" and "45 A".
    1. You can use the "Presets" selector, or enter the values into the text boxes.
  6. Press "To Set" and wait until the current becomes the set point (SP) and "HOLD".  It takes 23 minutes.
  7. Set "1 A/m" and "63 A".
  8. Press "To Set" and wait until the current becomes the SP and "HOLD".  It takes 18 minutes.
  9. Set "0.5 A/m" and "74.78 A".
  10. Press "To Set" and wait until the current becomes the SP and "HOLD".  It takes 24 minutes.
  11. Switch to the persistent mode, if you want.

Reference: UVA elog 154

To Switch to Persistent Mode

  1. Press the Toggle button of the main switch heater.  It turns off both the main and shim switch heaters.
  2. Press "To Zero" and wait until the current becomes 0 A and "HOLD".  It takes 4 minutes, where the ramp rate is slow at the beginning.

To Switch from Persistent Mode

...

To Ramp Down

...

Unlocking Controls

All controls on VI are usually locked, to avoid mis-operation.  When you need controls, you have to click the "All Controls: Locked" button.  It is preferable to apply the lock when you finished controls.

Image Added

Procedures

(A) To Ramp Up

(B) To Switch to Persistent Mode

(C) To Switch from Persistent Mode

(D) To Ramp Down

...