Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

FocusTaskResponsible personStatusNotes
Warm gHe circulation



Ongoing

Fridge and roots exhaust
Magnet path

Cold gHe circulation





Circulation test for QT


Dustin, Ishara

Done

Transfer-line → getting back via vaporizer is done 

Slow Controls Rack

Lakeshore testing (We tested the hardware but only a few channel. We need to test all of 8 channels):

  • Test 8 channel of the readout for all Lakeshores in the counting house
  • Test the LabView-VI using laptop in the counting house & decide which version of VI that we use
  • Test the Lakeshores readout in the rack after the fridge/stick in place and read from the target computer

MKS 670:

  • Produce/purchase the cable, and install Baratron 1000 Torr sensor
  • Produce/purchase the cable, and install MKS615 sensor

Purchasing (a total of ~$ 4,300 for items related to SC/magnet rack needed to be purchase:

  • Purchase ~$1,900 with UVA account
  • Arrange other institution to purchase another ~$2,400 items

Fridge-valve control:

  • Build the mechanics

Backup cable

  • Produce and install the cable or Lakeshore, AMI1700, etc after the order from Digikey arrive
  • Install the cable after the order from Pfeiffer and AMI1700 arrive

Automatic Annealing backup:

  • Finish the labview
  • Send to Fermilab and test the VI from target computer

ORC:

  • New Annealing box
  • Final SC Rack

Working on it 

Waiting the cable, need to have backup plan

Waqar, Kenichi






Kenichi




??





??




??



??

  • The fridge reading was completed.
  • The insert reading?






  • The cable parts were delivered.
  • Will assemble cables and connectors.








We have something that works 






Working on it



Start work

Magnet Rack

AMI1700 testing:

  • Put liquid nitrogen, and test the readout all the way to PLC (the AMI readout should be consistent with PLC readout)
  • Test the Labview VI or browser based readout
    (not urgent)

Mercury ITM:

  • Test the VI from the target computer

Maxigauge:

  • Fix the VI readout (currently the instrument readout and VI does not match)

Magnet & Shim PS:

  • Check the DC voltage/current on the cave side of the cable

Pressure sensor:

  • Install Aux sensor

ORC:

  • Final Magnet Rack
  • Automatic annealing box


Waqar, Kenichi




Kenichi


Zulkaida



??


??


??

Done




DoneZulkaida



Will compare them at low pressure.





Waqar and Sam are working on having the readings on HMI.


Need to find variable names for LHe and LN2 levels

In-cave piping and other pumping
  • Setting up the safety manifold to be pressure tested
  • Pressure test for helium safety relief manifold
  • Installing the manifold with the Rigging team
  • Installing insulation for LN2 supply line
  • Installing remaining gHe hoses
  • Installing two relief valves (gHe safety, gN vent)

Pressure test was completed for both Magnet Dewar and Manifold.
Fridge &  Target stick & insert
  • Install all temperature sensors
  • Install heater/annealing plate + sensors
  • Install Fridge in the Magnet
  • Setting up He3 level probe
  • Target insert test: Connect to Lakeshore to see the temperature sensor

Waqar is working on fridge
NMR
  • Noise test comparison between UVA & NM4
  • Ask Kun what's the plan (maybe the long term plan) with LANL rack
  • Preparing for 2 channels available for UVA-NMR

Kun will move to other place and will switch between UVA-LANL NMR
Thermocouples (Temperature sensor)

Install MCC E-TC and sensors and testing.

Kenichi
  • Completed

Microwave systemOrder parts?
Vibodha will working on it
PLC & QT & RootInstalling thermocouples to check the LCW temperatures at the coldhead compressors' inlet/outletKenichi, Sam (ACU)
  • Installed all Selected the hardware.
  • Received the hardware on June 28.
  • Install them.
  • Tested the readout using simple VI.
  • Developing Set up VI.

https://labjack.com/All-Categories/thermocouple-daq

  • Omega Type-J TC
  • LabJack U3-LV
Operation Manual Documentation

How to operate

  • Turbo Pump
  • Magnet & Shim PS
  • QT PLC



Continous/routine tasks
  • Ordering LN2 (reminding Kun ahead of time)
  • Filling LN2 purifier
  • Checking LCW parameters
  • Checking levels
Undergrad students

elog
Zulkaida

Engineering notes
Vibodha

Cryogenic Control Panel
  • Fridge, Insert sensors
  • Fridge valve controls
  • Need to get info from level probe
  • have P&ID on screen
Kenichi
  • Can control the fridge valves already.  Will calibrate parameters once hardware gets ready.
  • Which level probe?
  • Include P&ID when having a time.

Leak checkingHigher level leak-checker


LHeCheck , take photos from Messer


Others



...