  1.  If the system is OFF, then follow the steps on UVA-NMR system start-up.
  2.  Ensure that you identified the channel mapping between the Q-meter box and the target insert in the cave.
     Once you identified it, please write it on the Physical Logbook with the date and time. Then, ask the "Target Expert" to add a uva-elog entry regarding that.
  3.  This is the 3-channel Q-meter box located on top of the UVA-NMR rack on the cryoplatform.
     ImageImage Added
  4.  The first step is the "Diode mode tune" for each channel (one-by-one).
  5.  Locate the back of the Q-meter box and identify where the lambda/2 cables connect to the Q-meters.
     NMR signal cables = lambda/2 cables.
  6.  Select the channel you want to tune.
  7.  
  8.  Phase mode tune
  9.