Do Immediately | Additional Information | Task Finished Result | Person of task |
---|---|---|---|
Fridge sensors | 1KOhm Ruthenium Oxide | ||
Preparation for the dock survey | setup tooling table and position magnet and detail survey layout with crew | http://dbweb5.fnal.gov:8080/ECL/spin_quest/E/show?e=359 | |
Determine and measure true path for all cables coming from target cave and order all cable needed | Front Penetration → Racks on Cryo platform → Counting House Side Penetration → Racks on Cryo platform → Counting House | ||
Replace Black BUNA-N O-rings | Measure existing O-rings and find PTFE (Teflon) equivalents
| ||
After replacing seals setup safety walk through with | Setup Operational Readiness Clearance (through Rick) | ||
Buy a flaring tool for copper tubing | |||
Assemble and test microwave system | Needs to be shipped from UVa - 7/17/19 Borrow gore cable from UVa Need waveguide too | ||
Get Liverpool NMR Q-meter (and ancillary equipment) from LANL | |||
Setup temp full microwave system for testing here | |||
Setup sensors on stick | Check with lakeshore | ||
Stink test in the target loading area | with "special" spray | ||
Setup and test manometer | |||
Setup external magnet sensors with data going into slow controls data stream | |||
Shim Microwave actuator bushings for hard stop and top target. Microwave table and magnet should be in place and use the information from initial survey to measure | |||
Setup LANL NMR system for testing in counting house target area | |||
Setup UVA NMR system for testing in counting house target area | |||
Make material filling station | tub and accessories for fill the target insert | ||
Finalize microwave control system with stepper motor | |||
Setup actuator with potentiometer and controls |
Things to do when not working on the immediate things | Additional Information | |
---|---|---|
Setup Polarized Target Drone | Drone to control instide the cave | |
Setup Target Rack | Stepper motor drives and power supplies ADC for position readbacks Microwave EIP Lakeshore 218 x2 Level Probe Readout Turbo readout and Controller IV gauge readout Teledyne Hastings readout 4He & 3He manometers Possibly Microwave Power Supply Target Insert Lakeshore Fridge Lakeshore External Magnet Lakeshore
| |
Get hoses for microwave (EIO) | Either hard plastic or rubber | |
Target Controls Computer | Josh will find it | |
All cabling from target to racks and counting house | need lengths and to order cables | |
setup target operator station | ||
setup target loading station | ||
Finalize NMR | testing still needed | |
Target handler and alarm system | ||
Setup NMR VI | ||
Annealing controls | ||
Setup and test Main Gate Valve | ||
Test Air-core cable with EIP/microwave | ||
Setup Insert and leak check and electronics check, sensors, coils, SMA | ||
Setup Nuc and oscilloscope and PDP | ||
Setup Roots stack controller and power | ||
Get some plastic tubs and foam dewars |