- UPS System Setup for IVC
- UPS specifications Insulation Vacuum Page
- Power outages In the past and recent Insulation Vacuum Page
- We are in the loop with Steve Chappat to put the UPS; he will make a walkthrough soon
- Replacement of the flow controller (MFC) for the magnet return line
- HA was submitted and approved.
- Exchange of the flow controllers on the QT Manifold
- HA was submitted.
- Cleaning the outside gHe tank
- We have the procedure on the confluence page Cleaning gHe outside tank using the purifier - Wiki Post Portal - Confluence (virginia.edu)
- we need to submit it on DocDB and approve it soon.
- Cleaning Purifier
- After cleaning the gHe tank, we should clean the purifier to remove the contamination from the gHe tank cleaning.
- Needs to backfill the Magnet and the fridge with gHe — Completed on Apr. 18.
- Test the turbo pumps on the IVC (Insulation Vacuum)
- Turn ON the both Backing Pump (ACP 15) and the turbo pump (TMU 1001P)
- Turn OFF the turbo Pump (TMU 1001P) and keeps ON the backing pump (ACP 15)
- Turn OFF the backing pump (ACP 15) and keeps ON the turbo Pump (TMU 1001P)
- Install the HiCube 300 ECO on the IVC through the KF25 Tee connection
- Keeps turning ON the turbo pump (TMU 1001P), Backing Pump (ACP 15), and the HiCube 300 ECO.
- Turn OFF the turbo pump (TMU 1001P), Backing Pump (ACP 15) and keeps running the HiCube 300 ECO.
- Remove leaks from the IVC (Insulation Vacuum Chamber)
- We will receive our UVA Leak checker at the end of this week
- Both Liq's A and B should be running and in production mode.
- Both should need to be produced 4L/h
- Load gHe bottles into the system
- We do not have much helium in the outside gHe tank
- We do not have a procedure.
- Helium boil-off from the commercial dewars
- We have two commercial dewars.
- Boil-off procedures are approved.
- The engineering note is still under review
- I need a Certificate of Compliance from IdealVac.
- Heat tapes for the IVC and the fridge turret
- Commercial products of the heat tape and the power controller were approved by Mike.David Mertz
- A metal-box enclosure for the power-controller circuit is being designed.