Activity | 7/25 Go-Live | 8/1 Go-Live |
---|---|---|
Development | 5/27 | 5/27 |
Internal Testing (see Testing Plan below)
Internal Testing:
| 5/30-6/10 (2 weeks) 6/13-14: Vanessa to reserve blocks for testing. | 5/30-6/10 (2 weeks) |
Unit Testing (see Testing Plan below)
| 6/13-24 (2 week) Kick-off Planned during FST RBA Meeting on 6/16. (1-hour) | 6/13-7/1 (3 weeks) |
E2E (1 week)
| 6/20-24 (1 week) | 6/27-7/1 |
Updates from E2E (1 week) | 6/27-7/1 (1 week) | 7/4-8 |
Extend Promotion (Thurs) | 6/30 | 7/7 |
Move to Prod (1 weeks) | 7/4-8 | 7/11-15 |
Regression Test in Sandbox & update prod (2 weeks) Note: No SBX refresh on 6/25 or 7/2 | 7/11-22 | 7/18-29 |
Go-Live (HCM & FST RBA) | Monday, 7/25 | Monday, 8/1 |
- Training & Communications
- Will FST build any RBA training? (HCM and SIS didn't do any training)
- HR created a diagram and web page, SIS, UBI, DIS created web pages
- RBA links to the web pages that include the process flow and roles
- For FST:
- Include a Quick Reference Guide (or job aids)
- Documentation/Description of the roles so they know what should be requested
- Focus materials on what they are requesting
- Do not need training - the above documents should be sufficient
- Work with FST Communications/Training team to put on a web site
- Next Steps:
- Teresa to send links to HR and SIS pages to Sue
- Sue to speak with Augie & Bill Ashby for approach confirmation
- Christine will give Scott a heads-up
- Bill to speak with Scott Adams - and Scott to talk to Communications/Training team to create pages for FST
- Identify Communications Roll-out - talk to Brandy (will need interim approach and web pages)
- Data Steward Communication
- No training needed - need to explain the new framework and reminder of their role as a data stewards.
- We will include some data stewards in testing.
- Lisa will draft and review with Sue - perhaps sent by Augie or Bill.
- MBU Approver/Sr. Dept Finance Approver Communication
- Need the final list to receive a communication
- Christine to draft communication
- Need to provide clarity on what they are asked to approve and why they were selected.
- Leverage existing communication/documentation that she's worked with
- Coordinate with Lisa Emmons
- HR App Users
- HR Web Site updates (remediated app)
- Kelli and Teresa to contact Susanna Fuller about changes (Kelli scheduled call for 6/13)
- Significant update to role definition
- The new UI steps need to be updated on the Web Site.
- HR Data Steward Communication (Susanna Fuller)
- HR Web Site updates (remediated app)
- Cutover
- Can we do a soft launch with a subset
- Talk to Augie on Monday 6/6
- Interim process before RBA is live - working with FIN help desk.
- Monday 6/6 meeting with Teresa, Nicole, Sue, Augie
- Can we do a soft launch with a subset
- Cutover Planning:
- Finance Sec Groups will not be in Prod when we migrate - so the report will need to be updated in prod after the security groups are avail.
- Leslie will draft the cutover plan
...
- FIN Draft on the Teams site - ready for Matt to create the groups and update the BP
- Timeline
- 6/10: Matt to complete HCM Report & confirm FIN Report (target is 6/10 - priority is BP)
- 6/10: Kelli to update role names with _C and _NC naming convention
- 6/8: Final Spreadsheet available (need Data Stewards & backups)
- We have what we need
- Expect to have additions.
- TAPP Ticket to update requests:
Jira server TAPP columnIds issuekey,summary,issuetype,created,updated,duedate,assignee,reporter,priority,status,resolution columns key,summary,type,created,updated,due,assignee,reporter,priority,status,resolution serverId 1bc6018e-9860-3384-9a2a-a855ec4aabe6 key UVA-322
- 6/13: Ready for Unit Test
Testing Plan
- Internal Testing (DEV environment)
- FST: Teresa, Kelli, Crystal, Sue
- Test Planning
- Who would they like testing (Data Stewards and Sr. Dept Finance Approvers and requestors),
- Do we want to stage test cases for E2E testing?
- Verify the key testers are Nicole, Sue, Crystal
- Teresa, Nicole, and Sue will develop the test cases
- Internal Testing (DEV environment)
- FST: Teresa, Kelli, Crystal, Sue, Nicole
- HCM: Teresa, Kelli
- Unit Test Scenarios
- Teresa: Review HR Unit Test Scenarios & draft FIN scenariosTeresa/Sue/Nicole: Identify FIN scenarios
- FST Unit Test Scenarios have been loaded to TAPP. See UVA TAPP Workflow - Testing for accessing, testing, and passing scenarios in TAPP.
- Unit Testing (2 weeks)
- Schedule Kick-off - plan for Thursday 6/16 meeting. Should we extend to 90 minutes?
- Phase 1: Project Team Testing
- Sue, Steve, Nicole, Christine, Kelli, Teresa, Crystal
- Anyone else from HR (HR Remediation) - Amanda, Travis, Tim, Syed
- phase 2
- with WD Support Team: Sue Clements, Josh Breeden, Jonathan Agop, Tommye Arnold, Lisa Atkins, Mandy Eames, Nancy Honeywell, Thomas Schneeberger, Rylee Wiley
- Integration Testing
- Sri, Simon
- HCM: Venkat
- (Aarati Sonkusari also?)
- Kelli, Crystal
- Note: Data is UVA3
- Logistics:
- Book hour-long testing sessions.
- Need to know who will test so can stage test data
- Will provide a demo
- Phase 1: Project Team Testing
- End to End Testing (1 week)
- Data Stewards
- OSP (Urmila Bajaj, Michael Priddy) - they are requesting information about security requests
- Procurement/Spend: Sue to ID
- Sue will identify based on list of data stewards
- Sr. Finance Departmental Approvers - Sue and Nicole to identify a few (Blake, Kirby)
- Training Group - Patty Marbury is training lead
- Scott Adams - FIN IT (Admin Services)
- ITS Help Desk
- Finance: Andrew Sallans, Joey Carls
- for anything related to access to Huron/Research UVA, Vonda Durrer and/or Shenika Knox would be good to contact
- Data Stewards
...