ProcedureDocdb IDPreviously ReviewedSource file available?Not a procedure
1QT system startup and shutdown 10364NoYes
2Pumping and purging (generic)10184Yes (Rick)Yes
3Leak checking (generic) 10188Yes (Rick)Yes
4Dewar evacuation10178Yes, HAYes
5QT Purifier LN2 fill 10337Yes (Jordan)Yes
6Magnet pre-cool 10032Yes, ORC-2056.01Yes
7Magnet cooldown9651Yes, ORC-2056.01Yes
8Magnet operations 10062Yes, ORC-2071Yes
9Magnet fill from commercial LHe Dewar 10056Yes, ORC-2056.01Yes
10Magnet LHe fill9670Yes, ORC-2056.01Yes
11Magnet shield LN2 fill 10337Yes, (Jordan)Yes
12Outside gHe tank refill 10198Yes, (Jordan)Yes
13Routing NMR cables 10357Yes, HAYes
14UVA-NMR system shutdown,startup,tuning, data-taking10367NoYes10308
15Slow Control System turn on/off10369NoYes
16Annealing System turning on/off10372NoYes
17Adjusting the Parallel plate valve PSV-401-He10333Yes (Rick)Yes
18Fridge LHe fill 10375Yes, ORC-2056.01Yes
19Filling magnet shield with portable LN2 Dewar10053Yes, HAYes
20Manually vented He Gas Storage Tank to the Atmosphere10285No (Sent to Rick)Yes
21Leak Checking in the Cave (Target Magnet) 10308Yes, (Rick)YesNo
22HR3 Compressor Oil, Oil filter replacement10320NoYes
23Helium boiloff capture procedure 10282In ProgressYes
24Handling Target material NH3/ND310360In ProgressYes
25Filling the portable handheld dewar10358In ProgressYes
26Cold-heads warm-swap procedure10378Yes, HAYes
27Target lifter system powering up and shutting down procedure 10381NoYes
28Filling Purifier LN2 space using portable LN2 Dewar10053Yes, HA (Jordan)Yes
29Procedure for draining LCW from roots pumps10384Yes, HA (Rick)No (scanned from HA)
30LHe transfer using commercial LHe Dewar in the cave9670Yes, HA (Rick)No (scanned from HA)
31Microwave system powering up, Operation, and shutting down10387NoYes
32LHe transfer to QT storage dewars 10389Yes, HANo (scanned from HA)
33Installation of stinger into a Liquid Helium dewar10392NoYes
34Cold LHe Transfer with QT-transfer line10395NoYes
35QT Liquefier Dewar level cleaning and Dewar cleaning10401In ProgressYes
36UVA-QT Purifier Helium Space Cleaning Procedure10404YesYes
37UVA-QT Purifier LN2 Space Cleaning Procedure 10407YesYes
38Handling Target material CH2/CD210411In ProgressYes
39A Detailed description of upcoming plan10417In ProgressYes
40Plan for the usage of Ammonia for the target10414In ProgressYes
41Target insert loading/unloading procedure10355In ProgressYes
42Cleaning Procedure of roots LCW regulator10420NoYes
43Oil refilling/changing for rotary vane pump10422NoYes
44Target material dewar filling from the portable handheld dewar10427No Yes

...