Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.


Print this checklist and have it with you while proceeding with the following steps:

View file
nameMagnet_LHe_Fill_Checklist.docx
height250


Preparation:

  1. Check the outside gHe pressure and make sure it is below 90 psi. If it's equal, near, or above, then relieve its pressure down to ~80 psi.
  2. Check with Target Expert on Shift whether the REGX green hand valve is fixed to some pressure during the previous fill.
  3. Connect to the Cryo Control Computer (via VNC: see Polarized Target System for SpinQuest at FNAL for the instructions)

...